Opening of new Private Sidings/Private Freight Terminals: (Greenfield projects) (When consultant is engaged)
|
Sl. No. | Service | Time limit | Single Window Agency (to be contacted for progress/non-compliance) |
1.1 | In Principle approval | 30 days | CTPM (ctpm@wcr.railnet.gov.in) |
1.2 (a) | Detailed Project Report (DPR) approval | 30 days | CTPM (ctpm@wcr.railnet.gov.in) |
1.2(b) | Drawing Approval | 30 days (without bridges) 60 days(with bridges) | CE(G) (cegn@wcr.railnet.gov.in) |
1.2(c) | Estimate Approval | 30 days after date of submision | Sr.DEN(Co) of concerned division |
1.3 | Divisional certification after execution of the works | 30 days | Sr.DOM & Sr.DEN(Co) of concerned Division |
1.4 | Signing of siding agreement | 15 days | Sr.DCM of concerned division |
1.5 | Notificationafter certification | 5 days ( after receipt of Completion Certificate and signing of siding agreement and land agreement) | CCM/FM (ccmfm@wcr.railnet.gov.in) |
Activities to be performed by the party 1) Submission of application with feasibility report and conceptual / schematic plan. 2) Remittance of Rs.15000/- (non-refundable) towards feasibility study fee drawn in favour of Chief Cashier/FA&CAO/WCR. 3) Application for RTC to Railway Board either by Railway or by the party. Activities involved by Railway 1) Examination of the proposal with regard to feasibility, adequacy and flexibility. 2)Time limit: 30 Days Back |